Bilateral Compliance Agreement |
Jun 3, 2024 |
| Open | Bilateral Compliance Agreement |
Open |
COMPLETE PLAN REVIEW |
|
Sep 1, 2024 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Oct 10, 2024 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Nov 10, 2024 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Dec 10, 2024 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Jan 10, 2025 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Feb 10, 2025 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Mar 10, 2025 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
Apr 10, 2025 |
| Bilateral Compliance Agreement |
Open |
REPORT ARSENIC MONITORING |
|
May 10, 2025 |
| Bilateral Compliance Agreement |
Open |
CORRECT WATER QUALITY DEFICIENCIES |
|
Jun 10, 2025 |
| Bilateral Compliance Agreement |
Open |
MCL Violation Notice - Superseded |
Feb 27, 2024 |
| Jun 3, 2024 | MCL Violation Notice |
Closed |
RESTORE TREATMENT TO EFFECTIVE OPERATION |
|
Mar 28, 2024 |
Overdue
| MCL Violation Notice |
Closed |
SUBMIT COMPLIANCE ACTION PLAN |
|
Mar 28, 2024 |
Overdue
| MCL Violation Notice |
Closed |
ISSUE PUBLIC NOTICE |
|
Mar 28, 2024 |
Mar 12, 2024
| MCL Violation Notice |
Closed |
MCL Violation Notice |
Nov 13, 2020 |
| Jan 14, 2021 | MCL Violation Notice |
Closed |
SUBMIT COMPLIANCE ACTION PLAN |
|
Dec 13, 2020 |
Jan 14, 2021 - Late
| MCL Violation Notice |
Closed |
SUBMIT CONSTRUCTION PLAN |
|
Dec 13, 2020 |
Jan 14, 2021 - Late
| MCL Violation Notice |
Closed |
Other Compliance Schedule |
Jun 1, 2017 |
| Jun 29, 2017 | Other Compliance Schedule |
Closed |
REPORT LEAD & COPPER TAP MONITORING |
|
Oct 10, 2017 |
Jun 29, 2017
| Other Compliance Schedule |
Closed |